Advancing Solar Projects with Ground Grading
Ground grading, a crucial civil engineering process in solar projects, involves assessing and preparing the terrain—through earthworks like cut-and-fill—to create flat, vegetation-free surfaces that optimize equipment placement, enhance solar park performance, reduce construction challenges, and inform cost and environmental impact analyses.
The solar industry is constantly innovating and improving, yet there are staples of any solar park that are present in every project. Understanding what to expect at the beginning of the construction and knowing how to navigate potential challenges, or how to avoid them altogether, could greatly boost the performance of the solar park, as well as reduce expenses.
What is ground grading?
Assessment of the terrain is fundamental to any solar project. Simply put, ground grading is the process of checking whether earth preparations will be required at the location for the solar park. Terrain analysis can be used to evaluate uneven surfaces and similar disturbances in order to check the land assigned to a project. After that, a ground grading calculation—ideally performed within advanced solar design software—shows how much work needs to be put into the location in order to create a flat surface and remove vegetation for easier construction.
Ground grading is not exclusive to the solar industry, and due to its widespread use, it can be known by several different terms, such as earthworks or cut-and-fill. Either of the terms describes the act of altering the surface of the land.
Essentially, ground grading is one of the most reliable means of improving the project’s viability. It provides the analysis of how much it would cost to place the equipment in suitable locations for maximum performance and provides input for the civil engineer to determine the impact that earthworks would have on the project.
Ground grading and civil design
Ground grading falls under the umbrella of civil engineering. As a broad concept, in terms of solar, civil engineering takes into account the overall planning and construction of the plant. This includes evaluating location and determining water drainage, soil suitability, and environmental impacts.
Ground grading, on the other hand, focuses directly on the assessment of the PV area. In a scenario where there are plans to build a solar park in a location near cliffs, the civil design could evaluate the environmental impact the project might have and create a design for the park. Ground grading is then needed to prepare the location for construction, including moving the earth around to create a flat surface or removing obstacles such as trees.
The combination of both is essential to successfully determine the location of a solar park. Additionally, ground grading requires oversight from civil design to ensure the project’s costs won’t rise too much; the intricate relationships between the two also keep the maintenance of the project manageable. In worst-case scenarios, a lack of understanding or preparation for ground grading or civil design could result in exponential losses.
Ground grading costs
The cost of ground grading consists of several elements. The first one is the expense of preparing the surface for a solar park. This can be anything from cut-and-fill operations of displacing ground to removing bumps and placing it somewhere else to fill out the dips; it can also include the removal of boulders, trees, and similar obstacles. Ground grading can become an expensive endeavor, especially in more remote locations, since the ground work includes both transportation and labor costs. Additionally, civil design can point out any major problems with the land, such as stony conditions or water drainage issues.
The second element of the overall cost is maintenance. This is more applicable when the project requires modifications to the land. Let’s say the park is being built on uneven ground and in order to flatten the surface, modifications to the land were done, including shifting some of the ground around. This can cause instability, and in certain situations, this can lead to landslides or similar displacements, which can damage the park and require additional investments to keep the project operational.
Minimizing ground grading expenses with PVcase Ground Mount
Fortunately, there are ways to offset the ground grading costs without sacrificing the efficiency of the project. By utilizing CAD solar system solutions like PVcase Ground Mount, engineers can resolve collision and slope issues through a visual reflection of the data on the plan to accurately determine the pole length range and slope limit.
Additionally, the cut and fill calculation will show the value of the number of earthworks required. It allows the engineers to predict the viability of a project, as well as determine the potential costs. The ground grading feature ensures the solar project has all the information regarding the earthworks and the attached expenses.
Related
The Importance of Topographic Data for PV Design
Topographic data is crucial for profitable PV design as it enables accurate 3D site mapping, slope assessment, and constraint identification, but challenges include the difficulty of accessing geolocated, usable data and managing large data sets, which tools like PVcase Prospect address by consolidating public and premium data to streamline land analysis and reduce time and costs.
Case study on ground grading | PVcase
This case study compares terrain-following trackers (TFT) and traditional single-axis trackers (SAT) using PVcase software to analyze differences in site preparation, installation costs, and project timelines by designing TFT layouts that adapt to terrain profiles and evaluating the physical materials and work required for each tracker type on the same site.
Your First Project with PVcase Ground Mount Webinar
The on-demand webinar, led by Jonas Žemaitaitis, Technical Support Team Lead, provides a comprehensive walkthrough of the PVcase platform with a live demonstration of PVcase Ground Mount, teaching viewers how to enhance solar project efficiency, accuracy, and profitability through streamlined design workflows.
Zimmermann Tracker integration update | PVcase
PVcase and Zimmermann PV-Tracker have collaborated to integrate Zimmermann's innovative cardan joint technology into PVcase's Ground Mount software, enabling terrain-following single axis tracker layouts that significantly reduce earth movements and DC mismatch losses, as demonstrated in a 50 MWp Spanish project where using cardan joints cut ground movements by up to 95%.
Ground Mount
PVcase Ground Mount is an end-to-end solar design platform that automates terrain-adaptive layouts, slope and shading analysis, 3D cabling, and yield estimation to reduce project design time by 90%, enhance accuracy on complex landscapes, and streamline early-stage yield checks, as praised by industry professionals for improving efficiency and precision.
The impact of environmental hazards on solar projects
The article highlights that increasing environmental hazards like floods, wildfires, and extreme winds pose significant, often overlooked risks to solar projects, leading to costly financial impacts including wasted investments on unsuitable sites, expensive redesigns, liabilities in mergers and acquisitions, and increased operational damages and downtime due to reliance on outdated hazard data and insufficient risk analysis.